The interchange at "Kalina" required even more than a billion rubles.
An additional 1.1 billion rubles will be allocated to complete the transport interchange near "Kalina," Deputy Minister of Transport and Road Management of the Sverdlovsk Region Natalya Novitskaya said at a press conference. Her words were reported by the portal 66.RU.
According to her, the additional funds are needed "to continue and, hopefully, complete the work."
The overpass was originally scheduled to be completed in 2023, but the deadlines were postponed several times. Authorities now expect the facility to be ready by the end of 2026.
During that time the cost of the project rose from 6.6 to 8.8 billion rubles. The general contractor for the construction is a company that is currently undergoing bankruptcy proceedings. Despite this, the mayor's office does not plan to terminate the contract in order to avoid further delays.
Другие Новости Екатеринбурга (ЕКБ166)
The interchange at "Kalina" required even more than a billion rubles.
Another 1.1 billion rubles will be allocated to complete the construction of the transport interchange at "Kalina". This was announced by Natalya Novitskaya, Deputy Minister of Transport and Road Management of Sverdlovsk Oblast, at a press conference.