The reconstruction of the Yekaterinburg Circus is planned to be completed in 2027.
On July 15, 2026, the Yekaterinburg Circus, which began reconstruction in early 2023, will not open before 2027. This was reported by the publication "FederalPress," citing the general director of Rosgoscircus, Sergey Belyakov.
The cost of the work during the reconstruction has increased from 2.25 billion to 2.89 billion rubles. In 2026, 735 million rubles will be allocated for construction work, and in 2027—almost 24 million. The work is being carried out as part of the national project "Culture."
Currently, the reconstruction of the Yekaterinburg Circus is only 55% complete—the dome has been restored, the entrance group is being faced, and the installation of columns is underway. The auditorium will become smaller but more comfortable, as the distance between the seats will increase, and the aisles will become wider. The area of the circus will increase by a quarter: the building will be equipped with rehearsal and training rooms, a separate block will be built for animals, and a viewing platform will appear on the roof.
Другие Новости Екатеринбурга (ЕКБ166)
The reconstruction of the Yekaterinburg Circus is planned to be completed in 2027.
The Yekaterinburg Circus, which began reconstruction in early 2023, will not open before 2027. This was reported by the publication "FederalPress," citing the general director of Rosgoscirk, Sergey Belyakov.