Further development of the Academic area is under threat.
The company "Rosseti Ural" stated that the issues with supply in the Akademichesky district are of an objective and systemic nature. For this reason, the prospective plans of developers are under threat.
Earlier, the director of the corporation "Atomstroycomplex," Oleg Minkin, told the publication "Signal Ural" that he was forced to freeze the construction of a complex of facilities, as the bill for technical connection to the power grids amounted to about three billion rubles.
— An objective requirement is the construction of a new power supply center — the 110 kV "Matveevskaya" substation and the construction of other 20/0.4 kV distribution network facilities. Specialists from "Rosseti Ural" conducted an assessment of the capital intensity of the projects — it amounts to several billion rubles, Minkin is quoted by the media.
Energy companies propose a cost consolidation mechanism, which involves distributing the amount among the participants in the development of the territory.
The company suggested that the Ministry of Construction of the Sverdlovsk region convene a meeting to develop a solution regarding the technical connection of construction facilities in Akademichesky.
Earlier, the Yekaterinburg city administration put a plot of land in Novaya Sortirovka up for auction for development.